Kajima Corporation

General contractor for data centers and other high-technology facilities. Kajima was appointed to build Princeton Digital Group’s large Saitama campus.

HQ JP Asia-Pacific Hyperscale work

Verified

Visit Kajima Corporation Compare with similar Request a quote

On the record

9 sourced facts
Regions Where the sources show the company building: regions named in its own pages plus the locations of its listed reference projects. Not a promise of service everywhere.
Asia-Pacific 1
Hyperscale work True where a source says hyperscale or names Meta, Microsoft or Oracle as a client. Confidential clients stay confidential and are never inferred.
Yes 1
Reference project MW Headline megawatts of the named reference project, as its source states them. Planned, contracted and delivered figures are mixed; the Reference project capacity field on each company page carries the basis. Never a company total.
100 1
Disclosed clients Clients, operators or tenants the source names, as short names. Their roles are under Client context. Never an inferred identity.
Princeton Digital Group, Lendlease 1
Client context The source's own wording on the named parties and their roles, for example tenant, owner or end-user, and any limit on the engagement.
Lendlease developer; Princeton Digital Group operator 1
Contracting role and services The role or scope the company states: whole facility, shell and core, construction management, MEP, EPC.
Appointed construction contractor; Nikken Sekkei is the designer 1
Reference project A named or confidential project from the company's own page. One project, not the whole portfolio.
Princeton Digital Group campus, Saitama City, Japan; Lendlease development 1
Reference project capacity and basis Source-reported project capacity with its qualifiers: electrical or IT basis, planned or delivered, the contractor's scope.
Close to 100 MW IT capacity planned across phased development; 2022 announcement, not proof of completed capacity 1
Completion or scheduled delivery Actual completion where stated, otherwise a labelled target.
Announced phase scheduled for 2024; actual handover not verified by this historical release 1

A project figure belongs to that project. It is not a company total, and a planned or announced figure is not a delivery. Fields the company has not published on the pages we read are left out.

Sources

  1. lendlease.com: aquila groundbreaking ceremony accessed 2026-11-11

Keep shortlisting

Get a quote from Kajima Corporation and similar companies

Tell us what you need once. We send it to matching companies and they reply to you directly.

Quote requests open shortly. To get in first, email hello@datacenterconstructioncompanies.com.